Erasmus Welcome Days and introductory lessons for most of our courses.
We chose the topic (Electronic buoy/beacon), gave several presentations and finished an assignment for the course 'Team Building'.
We did the first research to collect background knowledge about the topic. We also created a schematic diagram of electrical part of the project and started searching for particular components. At the end of the week we prepared the first proposal for the client.
After the meeting with the clients and supervisors, we had a better view on the prototype the client expected from us. We held a meeting with our group and brainstormed about all the things the clients and supervisors had said. Afterwards we started to make an engineering storyboard. After the storyboard was made, we wrote the second proposal which included the requirements for our electronic buoy.
We had a long and productive meeting with our supervisors on Thursday. On the same day we had a long discussion among ourselves during which we agreed on many points of our work on the project. On Friday we met at LSA with our clients and had a similarly efficient meeting that clarified many aspects. We then met on Sunday and talked over the things we had learned in the latest meetings. We made a plan of work for the next week. Our team work has considerably improved.
During the Easter Holiday we focused on individual work, everyone was doing his tasks allocated last week, especially preparing materials for State of the Art. Bennet started finishing marketing plan.
We visited Enercon (wind energy company) and Continental (tyre company) to see their factories from inside. We prepared the SCRUM sheet for the interim report sprint and tried to follow this schedule. We met prof. Fernando Ferreira for stainless steel structure consultation. We started intensive work on the interim report and presentation - till the end of this week we almost finished e.g. Sustainability, Ethics and Marketing part. We did deep research for State of the Art.
We wrote the 'State of the Art' and finished the interim report, because the deadline was on the 14th of April. We had to present our interim report on 18/4, therefore we made our PowerPoint presentation during the 8th week.
We presented our interim report on the 18th of April. Afterwards we brainstormed about the future project development.
After the feedback of the supervisors and the teachers, we started editing the interim report to the final version. We discussed about how the final version of the steel structure should look like and began with the drawings. Regarding this, we contacted Mr. Fernando Ferreira again to discuss our thoughts. We began with a electronic/wiring scheme and did extensive research about micro controllers. We also started with finalizing our marketing plan.
We worked on the final report. After the remarks of Mr. Fernando Ferreira we changed our drawings and brainstormed again. We continued with the electronic/wiring scheme and extensive research about micro controllers. We finalized our marketing plan.
We worked on the final report. We had a meeting with Mr. Fernando Ferreire again and he helped us with the steel structure. We continued with the electronic/wiring scheme. We did tests at LSA to find out the buoyancy force of the fibreglass hull.
We had two meetings with Mr. Mario Alvim concerning the buoy hull and solutions for making it waterproof. We finished the sustainability part.
Meeting with Mr. Alvim on Friday, 24.05. at LSA. He took the buoy back to ALTO in order to fix the broken parts of the hull. On Saturday we went to Multiborracha, Acessórios de Borracha e Plásticos, Lda. in Alfena to buy the EPDM rubber tape. Once Mr. Alvim fixed the hull, we will use the tape to seal the buoy clasp. Further, on 28/05 we spoke to Mrs. Malheiro and Mr. Ferreira to clarify the steel structure for a last time. Supporting triangles need to be added as well as a cover for the underwater part of the steel structure. In the mean time the final schematics were made.
At Dismotor-Comércio de Motores e Acessórios Lda. in Matosinhos all necessary parts regarding the mooring mechanism and lamps have been chosen. A pro-forma lists all parts. Also the steel structure has been confirmed and was handed in at the responsible workshop. During a test concerning the water-resistance of the hull it turned out that the clasp is not waterproof. We also have worked on poster, paper, final report, user manual, video, presentation.
During the last week everybody was confronted with finishing the project. We met every day at LSA in order to finish our final report, poster, paper, video, last but not least, the final presentation.
First EPS meeting, including introduction of the EPS supervisors, further proceeding and detailed presentation of the electable projects.
Second EPS meeting, the supervisors answered most of our questions. They guided us in the direction we have to go to develop the buoy (regattas). Web based user interface is optional. After the meeting they showed us the current buoy.
At the 3rd meeting with our supervisors we got to know that we should: create tables comparing different technologies characteristics of each component, create all important technical drawings (especially of stainless steel part of the buoy), consider ethical aspects of our product in the final report. Some of our questions could not been answered, because they depend on the needs of our client. In the end we were shown several examples of posters. Further we had a first meeting with our client. Our project became more clearer and we earned necessary information of what the client expects from us, as a team and also from the project. To make things even clearer, we are supposed to create an engineering storyboard, including both necessary functions (´environmental-measuring´ and ´regatta´) until our next meeting. For further processing, we measured the inside and outside dimensions of the buoy with a measuring tape.
This week’s meeting took longer than expected. We talked for over an hour, instead of the assumed 40 minutes, and then after the two other groups have finished, we met yet again. The meeting was therefore very productive and we obtained many answers to our questions. First of all, we learned that we are allowed to use sources in a different language than English. Secondly, we were instructed to make a list of materials with references to their price, weight, current and voltage. Thirdly, we got to know that there were already many components that we could use, but we would know them on Friday. Furthermore, we were explained in detail how the autonomous sailing boat regattas’ look like (boats of different size and shape, no human control from the beginning to the end, different position of the helm, different location and area of sails, different waterline, all boats start at the same time, handicapped formula etc.). Moreover, we were told that our buoy should send the data to a “world server”, optimally each second if possible, it should have gnss and CTD sensors, it should be able to work for at least one week for the environmental function and one day for the regatta’s function, and it must have a ballast. Additionally, we should consider providing the buoy with a servomotor for recharging the battery. The last point of our meeting regarded the “hardware box” which would contain the most important electronic components of our buoy, i.e. the control module, the communication module, the data storage module etc. We obtained a general vision of what it could look like and what characteristics it could/should have. At the second meeting that day, we discussed our proposal and storyboard for the client and made improvements accordingly to the suggestions of the supervisors.
The meeting started punctually but lasted more than we expected. During this time we were given several useful advices and suggestions. At the beginning we were shown some webpages where we can obtain meteorological data about Douro river (e.g. meteo.isep.ipp.pt; www.hidrografico.pt). We were also told that near the ocean the riverbed is mostly covered with sand. Therefore we should consider type of anchoring suitable for this condition. However, we shall recommend the client to buy 2 types of anchors: for sand and for rocks in case of future change of buoy location. We were adviced to visit Efurada - village where we can watch fishermen anchors. We should also think of safety mechanism to detach buoy from the anchor chain. Next, we discussed mechanical part. We were advised to do any forces calculations assuming that the buoy should stand approximetely 50 kg of additional load. We were given contact to Mr. Fernando Ferreira who could help us design properly the steel structure. Afterwards we were given some clues about what should we include in interim report (how our buoy is sustainable, how and why we chose the final solution of the product, what tests should be done in constructing phase). At the end we were told what are the issues we could start thinking about from this moment, like preparing electrical and signal schematic of the buoy.
Interim Presentation
Firstly we talked about the drawing of the hull we made. We discussed two types of connection for the antenna:
Secondly we discussed the choice of the GNSS sensor, the supervisors told us that the easiest way of choosing one, is to use the sensor LSA already has for the catamaran. Finally we talked about the different types of connections we proposed in the signal schematic. The supervisors mentioned that we can use self vulcanizing tape to make everything watertight. They also said that there are three layers in an interface: physical, protocol, electrical, so we have to keep these three things in mind.
Further:
Please register here all project activities
| Start | End | Task | Description | Who |
|---|---|---|---|---|
| 2013-03-01 | 2013-03-04 | Choose the project topic | / | All |
| 2013-03-06 | 2013-03-06 | Prepare the Second EPS meeting | We prepared our first general questions for the meeting with project supervisors. | All |
| 2013-03-07 | 2013-03-07 | 2nd EPS supervisors meeting | Description is in the minute. | All |
| 2013-03-08 | 2013-03-08 | Meeting about the tasks, task allocation and Gantt chart | We thought of main tasks and discussed in what areas each team member is the best. We discussed a Gantt chart outline. | All |
| 2013-03-09 | 2013-03-09 | Gantt chart | Bennet created complete Gantt chart. | Bennet |
| 2013-03-10 | 2013-03-10 | Meeting about defining the tasks | We defined all main tasks to do and finally decided on task allocation. | All |
| 2013-03-11 | 2013-03-11 | Do research for target market | / | Bennet |
| 2013-03-11 | 2013-03-11 | Do research for motherboard type | We were looking for information mostly about Adruino and Raspberry Pi. | Bennet, Konrad |
| 2013-03-13 | 2013-03-14 | Prepare the first proposal for the client | We decided what structure should such proposal have and what should it include. Bennet created the final version of the paper. | All |
| 2013-03-14 | 2013-03-14 | 3rd EPS supervisors meeting | Description is in the minute. | All |
| 2013-03-14 | 2013-03-14 | The “kick-off” meeting with the client (LSA) | We got to know what are main client needs. We had been given many important advices. We had been guided in how a correct engineering proposal should look like. | Bennet, Konrad, Toon |
| 2013-03-14 | 2013-03-14 | Measure dimensions of the current buoy | We measured all possible diameters, circumferences and heights inside and outside the current buoy. | Bennet, Konrad, Toon |
| 2013-03-16 | 2013-03-16 | Meeting to talk about the first proposal, plan the second proposal and start to make the storyboard | We discussed what should be improved in our proposal structure. We did the general research about storyboards. We created an outline structure of our first storyboard. | All |
| 2013-03-?? | 2013-03-21 | Prepare and write the first marketing plan | / | Bennet |
| 2013-03-18 | 2013-03-18 | Meeting to work on the project | We decided how our first storyboard for the client should look like, Toon drew the pictures. Konrad improved a schematic diagram of buoy components, Mateusz started to prepare a leaflet, Bennet was writing a marketing plan. Toon and Bennet discussed the “regatta mode” of the buoy. Konrad and Mateusz defined sustainability concerns that we should consider. | All |
| 2013-03-18 | 2013-03-20 | Prepare the first leaflet | Mateusz created the first lefleat which includes: team members pictures, short description of task, initial stage and purpose of our project, cartoon explanation of how our buoy is going to work. | Mateusz |
| 2013-03-18 | 2013-03-20 | Prepare the 1st revision of the proposal | We were working on improvement of our proposal. We defined all needed requirements. Toon put all storyboard drawings into Prezi presentation, created the general outlook and filled the main body of the paper. Konrad upgraded schematic diagram of electronic components and was responsible for adding last corrections to the document. | All |
| 2013-03-19 | 2013-03-20 | Short description of the project | Mateusz prepared a document shortly describing our project for an english class. | Mateusz |
| 2013-03-21 | 2013-03-21 | 4th EPS supervisors meeting | Description is in the minute. | All |
| 2013-03-21 | 2013-03-21 | Additional meeting with supervisors | We presented and discussed our first storyboard for the client and our improved proposal. | All |
| 2013-03-22 | 2013-03-22 | 2nd meeting with the client (LSA) | We presented our improved proposal. We talked with Mr. João Paulo Baptista about sensors. We have been given a wind speed/direction sensor. We have also been told that we should use compass to calibrate wind direction measurement. We talked with Mr. José Miguel Soares de Almeida who showed us 3 different microcontrollers available at LSA. We have also been given a CTD sensor. Mr. Eduardo Alexandre Pereira da Silva told us what are must-haves of our project. He instructed us in what should we prepare for the next meeting (e.g. quantify requirements, create technical drawing of steel structure, prepare state of the art about each component). We have been given an acces to laboratory building. | All |
| 2013-04-02 | 2013-04-02 | Workplan | Updating/Creating a workplan (product/sprint backlog) and gantt chart | Bennet |
| 2013-04-04 | 2013-04-04 | Visit to Enercon and Continental | We visited 2 factories of Enercon (the company producing wind turbines) and Continental tyres factory. | All |
| 2013-04-05 | 2013-04-05 | 5th EPS supervisors meeting | Description is in the minute (meeting was moved to friday due to the activity above). | All |
| 2013-04-05 | 2013-04-05 | Consultation of steel structure | We met Mr. Fernando Ferreira to discuss our concept of stainless steel structure. He gave us many very useful clues about designing the steel structures and helped us improve our concept. | All |
| 2013-04-05 | 2013-04-08 | Sustainability | Finishing the sustainability part and presentation | Bennet, Toon |
| 2013-04-08 | 2013-04-14 | Interim Report | Working on the report and presentation. (State of Art, Marketing Plan, Sustainability, Ethics etc.) Finishing it before sunday, April 14th | All |
| 2013-04-12 | 2013-04-12 | Consultation of microcontroller | At the additional meeting prof. Paulo Ferreira provided us with some general information about microcontrollers and possibilities of attaching particular interfaces. He also helped clarify description of microcontroller boards suggested by LSA. At the end he suggested what research should be still done and where to look for more information. | Konrad |
| 2013-04-13 | 2013-04-13 | Meeting to work on Interim Report | All | |
| 2013-04-18 | 2013-04-18 | Interim Presentation | We gave the 20min presentation about our progress at the meeting with all supervisors and courses' teachers. We obtained some comments and remarks about our interim report (especially regarding minor mistakes). | All |
| 2013-04-23 | 2013-04-23 | Measuring the hull | All | |
| 2013-04-24 | 2013-04-24 | Consultation of MCU board | Konrad | |
| 2013-04-25 | 2013-05-03 | LSA | Testing functionality of the buoy hull; Meetings about steel structure and electronic schematic | All |
| 2013-05-07 | 2013-05-16 | Improving/Testing/Meetings | Further proceeding on the steel structure/electronic schematic/buoy hull. Different meetings concerning the three main issues took place. New materials and components needs to be provided. E.g. rubbertabe, bolts, nuts etc. | All |
| 2013-05-21 | 2013-05-21 | Editing the sustainability part | / | Toon |
| 2013-05-24 | 2013-05-24 | Meeting with Mr. Alvim at LSA | Mr. Alvim took the buoy hull back to ALTO for repairing broken parts. Afterwards we had a Teammeeting and discussed further proceeding and essential steps for the next phase, the last phase. | All |
| 2013-05-25 | 2013-05-25 | Shopping | Bennet went to Multiborracha, Acessórios de Borracha e Plásticos, Lda. in Alfena to get the EPDM rubber tape (6,10 EUR) | Bennet |
| 2013-05-27 | 2013-05-27 | LSA Meeting | We met at LSA to work on the project. In a short meeting with Jose Almeida we asked about material/components LSA needs us to provide with. He explained that LSA is going to order at www.mouser.com . We are supposed to check, if the necessary material is available at this electronic store | All |
| 2013-05-28 | 2013-05-28 | Meeting | Discussing last decisions concerning the steel structure. The aim is to finish the structure till Thursday this week. | Mateusz, Bennet |
| 2013-05-29 | 2013-05-29 | Meeting at LSA | Measuring weights at LSA, start working with microcontrollers | All |
| 2013-05-31 | 2013-05-31 | Making the hull waterproof | We fixed a new rubber to make the hull watertight | Bennet, Toon |
| 2013-05-31 | 2013-05-31 | Microcontroller | We started to work with the microcontrollor and did research about programming | Konrad, Toon |
| 2013-06-01 | 2013-06-06 | daily Meetings | at LSA, working on the report, the steel structure, electronics and the clasp of the hull | All |
| 2013-06-05 | 2013-06-05 | Tests | water-resistance of the hull | All |
| 2013-06-06 | 2013-06-12 | Finalising | Report, Video, Paper, Poster, Electronics, Tests at LSA | All |
| 2013-xx-xx | 2013-xx-xx | Template | x.x.x.x.x.x.x.x.x.x.x.x.x. | All |